Tuesday, July 28, 2015

Long overdue update

A lot has gone on since my last post:
 
Framing done
Rough Plumbing, Electrical, HVAC, Prewire for network and distributed audio.
Drywall, garage door, Roof, Concrete in garage, and drywall finishing started..
 
Siding is slated for next week.
 
Following are random pics of the progress..
 
 

 
 



 
 
Garage poured


 
 
YAY POWER!!!
 
24 space in-wall rack
The new home for all of my audio toys!!
 





 


 
 
 
 



Thursday, July 2, 2015

Lots of Pics

 
 
These aren't in any particular order but lots of progress this week
 
 
 
 
 
about to set the first truss
 
 
2nd floor bonus room into finished storage
 
 
 
Hallway to bedrooms
 

 
Bonus Room
 
 
Through the wall to 2nd bedroom
 
 
Hall
 
 
Hall again
 
from bonus room through master 
 
 
 
Bonus room again
 
 
 
 
 
 
They installed the Panel today too
 
 
Front Entry
 
 
Dining room from entry
 
 
Family room to morning room
 
 
Study
 
 
 
Dining room / entry
 
 
Kitchen morning room
 
 
Kitchen to Family Room
 
 
Morning room
 
 
 
 
 
 

Tuesday, June 30, 2015

Progress!!!
Framing started on Friday and they seem to be progressing nicely.
I got approval to do my LV wiring last week so it looks like all of the pieces are beginning to fall into place. After moving from my old home and setting up temporary residence at my in-laws I'm looking forward to a week or so of semi-normal life.
 




Saturday, June 20, 2015

 
Not much to report except a lumber delivery. Supposed to start framing late next week due to rain delays from last week
 
 
 
 
 
 
 
 


Wednesday, June 17, 2015

Foundation in and backfill done.
 
Today they finished up backfilling and the steel is on site. I am hoping the framing package shows up tomorrow so they can start framing on Friday.
 
 
 
 



 

 
 


Tuesday, June 9, 2015

 
UPDATE
 
 
Poured the footer today.. I hope the 4 inches of water doesn't compromise the soil strength under the concrete. I am pretty sure that it wont be an issue but it is a bit concerning I would be really unhappy if I end up with un even settling due to poor soil conditions.
 
 
 
 
 
 
 


Thursday, June 4, 2015

They started digging today!! Now I'm getting excited... looks a lot bigger than on the site plan although it will shrink a bit when they backfill.. This is about 2 thirds dug  lots of clay in that hole. So much for a paver patio.